Development in the Albertine Graben is split into two massive upstream extraction projects feeding into a shared downstream transport network:The Tilenga Project: Operated by TotalEnergies in the Buliisa and Nwoya districts. It features roughly 400 wells drilled across 31 locations, aiming to pump 190,000 barrels per day at peak production.The Kingfisher Project: Operated by CNOOC on the southeastern bank of Lake Albert in Kikuube district. The facility is over 99% complete and targets a peak output of 40,000 barrels per day.East African Crude Oil Pipeline (EACOP): A 1,443-kilometre electrically heated pipeline that connects the Albertine fields to the marine terminal at the Port of Tanga, Tanzania. It is currently 84% complete.Uganda Oil Refinery: A planned 60,000 barrel-per-day facility located in Kabaale village, Hoima. It will refine a portion of the Albertine crude for domestic and regional usage.